March, 2011

Boiler Room
• Capitol Boiler replaced 3 tubes on Boiler #1 and 2 tubes on Boiler #2.

Smoke Detectors
• Smoke detectors were replaced in Buildings 1418, 1428, 1524 and 1538.

Storage Room Door Locks
• Door locks were replaced in 1403 & 1426.

Trash Room Light Fixtures
• Light fixtures were replaced in 1414, 1435 and 1554.

Entrance Door Repair
• Doors were repaired at 1421 & 1431.

Pole Light
• Pole light and ballast was replaced at 1402.
• Photo cell was replaced at 1433.

Leaks
• Staff replaced domestic hot water line and return in attic @ 1533-21.  Staff also replaced ceiling in 1533-21.
• Staff repaired pin-hole pipe leak behind toilet in unit 1423-12.
• Staff replaced hot water return line in the attic of 1522.
• All-Seasons repaired underground pipe leak near the boiler room, and in front of Building 1437.

Landscaping
• A&D Tree Services removed all downed limbs and branches from storm damage.
• A&D also removed large pine tree by the boiler room due to the underground leak.
• McFall & Berry are scheduled for spring clean-up next week.

Handicap Space Measurements
• Measurements were taken and put in digital file for future reference.